Off grid solar system UK guide: how to power an off grid cabin

Published Updated 11 min read

Small black timber off grid cabin with an off grid solar system on the roof and a wood burner flue, on a fenced hillside above a misty UK valley
One of the Unplugged off grid cabins, with solar on the roof. We designed and built the electrical systems for Unplugged's cabins. Photo: Unplugged

This off grid solar system UK guide explains the 6 main parts of a system for cabins, log cabins, shepherd’s huts and glamping pods with no grid supply. It also covers how we size it for a British winter, and how we test and certify the 230V side.

Quick answer

In short: how does an off grid solar system work?

An off grid cabin runs on solar panels charging a lithium battery through an MPPT controller. A Victron MultiPlus-II then turns the battery’s energy into 230V, and a Cerbo GX MK3 shows what’s left. We size the battery first, then the solar for UK winter light. Overall, that’s the off grid solar power system UK cabin owners ask us for most. Finally, we inspect and test the 230V installation to BS 7671.

  • Battery sized first, then the solar
  • Sized for December light, not June
  • Fogstar lithium as standard, Victron throughout
  • 230V side tested to BS 7671, with an EIC
230Vfrom a Victron MultiPlus-II inverter charger
1 screenCerbo GX MK3 and VRM for the whole system
EICissued for the cabin's 230V installation
Testedin our Witherslack workshop before it leaves

Book a free 30-minute call with Tom

On this page 12 sections
  1. In short: how does an off grid solar system work?
  2. What is an off grid solar system?
  3. What is needed for an off grid solar power system?
  4. Off grid cabin solar system sizing: how much solar do I need to be off grid?
  5. 12V, 24V or off grid 48v?
  6. Complete off grid solar system with batteries UK: kit or designed system?
  7. Off-grid solar system wiring diagram: why we don't publish a generic one
  8. Powering an off grid shepherds hut or glamping pod
  9. BS 7671 inspection and testing: is an off grid cabin safe?
  10. Off grid cabins and off grid log cabin projects: how we help
  11. Off grid solar system UK FAQs
  12. Sources

What is an off grid solar system?

An off grid solar system powers a building with no mains cable running to it. Instead, you make and store everything you use on site: panels on the roof or a frame, a lithium battery, and an inverter charger giving normal 230V. You export nothing, so there’s no grid connection to arrange.

So good off grid solar systems start from how you use the cabin, not from a kit in a box.

Too little battery and the system shuts down on the second grey day. Equally, too much solar on a small battery means you pay for energy you can never store.

We design off grid power systems from three facts: what you run, when you use the cabin, and how much winter light the site gets. The off grid electrical systems we build use Victron Energy equipment throughout, so the whole system reports through one Cerbo GX MK3.

What is needed for an off grid solar power system?

In essence, off grid solar power systems come down to a short list of parts, each with one job.

What's in the system

  1. Solar panelsRoof or ground frame, sized to your loads and site
  2. Victron SmartSolar MPPTCharges the battery from the panelsDC isolator at the array
  3. Fogstar lithium batteryLiFePO4, stores the energyFusing and isolation close to the battery
  4. Victron MultiPlus-IIInverter charger, makes 230VGenerator input when the sun is short
  5. Cabin consumer unitmetal, double-pole RCBO 230V circuits
Cerbo GX MK3 to VRM. Collects data from every Victron device, so you can check the system from your phone.
Simplified flow, not a wiring diagram. Instead, we draw every system for its own cabin.

01Solar panels

Panel size and count depend on your loads and your site, so we don’t put a figure on them until we know both.

02Solar charge controller

A Victron SmartSolar MPPT charges the battery from the panels. MPPT tracking gets the most from low, flat winter light, which is when a cabin system earns its keep. Also see our solar charge controllers guide and the controllers in our shop.

03Lithium battery

We fit Fogstar lithium batteries as standard. Victron’s data for lithium iron phosphate (LiFePO4) shows it holding its capacity over thousands of deep cycles and losing little energy in charging. So it suits an off grid battery that works every day. More in our battery types guide, or browse lithium batteries.

04Cerbo GX MK3 and VRM

The Cerbo GX MK3 collects data from every Victron device and sends it to VRM, so you can check the system from your phone.

05Victron MultiPlus-II inverter charger

This is the off grid inverter at the centre of the system. It turns battery power into 230V for the consumer unit and charges the battery from a generator when the sun is short.

Its internal ground relay links neutral to earth whenever there’s no AC input, so the RCDs still operate with no grid supply. We therefore set that relay and the cabin’s earthing up for a standalone system. Our inverter guide explains why we use an inverter charger rather than a plain off grid solar inverter, and the MultiPlus-II range is in the shop.

06Protection and distribution

Fusing and isolation on the DC side, close to the battery and the panels, and a metal consumer unit with double-pole RCBOs on the 230V side. Our guide to fitting a DC isolator to a solar installation covers the array end.

Fogstar Energy 48V lithium battery touchscreen showing 55% state of charge and 53.0V, with a blue data cable in the communications port
A Fogstar 48V lithium battery from one of our cabin systems, showing state of charge and voltage on its own display. Photo: Unplugged
Victron MultiPlus 48/1600/20 inverter charger on a blue board, with a Solar PV on Roof, Battery in Installation warning label
A Victron MultiPlus inverter charger on a cabin board, labelled for solar PV and a battery in the installation. Photo: Unplugged

Off grid cabin solar system sizing: how much solar do I need to be off grid?

We size a cabin solar system from the battery outwards. Here’s the order we work in.

  1. 01

    Start with daily use and days in hand

    To begin with, we take your daily use and the number of days the battery has to cover with little or no sun.

  2. 02

    Match the headroom to how the cabin is used

    A weekend cabin, for instance, may only need a day or two in hand. However, one let out through the winter needs much more headroom.

  3. 03

    Size the solar for the darker months

    Then we size the solar to refill that battery in the darker months, not in June.

  4. 04

    Read the site

    Site matters as much as size. For example, a cabin in an open field and one under trees in a wooded valley can need very different arrays for the same loads. In particular, hills to the south, tree cover and roof pitch all change what the panels see in winter.

  5. 05

    Plan the backup

    If winter use is heavy, the generator input on the MultiPlus-II is the backup. It charges the battery and powers the cabin at the same time, so a grey week in the fells doesn’t leave you without power.

For holiday lets

For owners in the off grid cabin uk holiday market, that’s the key point: we size a cabin let all year for December, not for the summer.

Black timber guest cabin with solar panels across the roof, a small deck and two garden chairs on gravel
A timber guest cabin with panels across the whole roof. Roof pitch, tree cover and the hills around it decide what the array sees in winter.

Running several units? For Business answers the common questions from cabin operators.

12V, 24V or off grid 48v?

Larger cabin systems usually run at a higher battery voltage, because the same power needs less current. As a result, less current means lower losses and more manageable cables and protection, which is why Victron’s Wiring Unlimited points bigger systems towards 24V or 48V.

Same power, less current

12V4× current
24V2× current
48V1× current

Current = power ÷ voltage. So if you double the battery voltage, the current halves.

Example: the current a 2,400W load draws from the battery
Battery voltage Current for 2,400W
12V 200A
24V 100A
48V 50A

Inverter losses add a little to each figure, but the ratio stays the same.

For that reason, we choose the voltage at design stage, from your loads and the Victron equipment that suits them. Our series and parallel wiring guide explains how you build batteries up to a system voltage.

48 volt board with a Victron Cerbo GX, GX LTE 4G modem, SmartSolar MPPT 150/45, PV array DC isolator and a 125A Class T fuse
The array end of a 48V board: Victron SmartSolar MPPT 150/45, PV array DC isolator, 125A Class T fuse, and a Cerbo GX with a GX LTE 4G modem.

Complete off grid solar system with batteries UK: kit or designed system?

Boxed kits exist, but a cabin works best with a system designed around it. A complete off-grid solar system with batteries uk sellers ship in a box can’t know your loads, your site or your winter use, and those decide everything else.

At Tiny Build Electrics, an off grid solar kit is a custom kit Tom designs after your consult, priced in Xero for your build. In other words, it isn’t a product off a web store. After that, you take one of two routes.

Route 1

Custom kit with Self-Build

Our Complete DIY Self-Build Package comes included free with the kit. You get the parts list and a wiring diagram drawn for your cabin.

Route 2

Fitted

We build the system as a ready-built Victron board in our Witherslack workshop and test it before it leaves.

Ready-built 48 volt Victron board on the workshop bench: MultiPlus 48/1600/20, SmartSolar MPPT 150/45, Cerbo GX, Lynx Power In 1000, battery isolator, generator inlet and two consumer units
A ready-built 48V Victron board on the Witherslack bench: MultiPlus inverter charger, SmartSolar MPPT, Cerbo GX, Lynx Power In, battery isolator, generator inlet and two consumer units.

Off-grid solar system wiring diagram: why we don’t publish a generic one

Why no generic diagram

Every cabin’s loads, cable runs and protection are different, so a generic diagram would mislead more people than it helped. Instead, the Self-Build package includes a diagram drawn for your build. For background, read our guide to selecting the right DC fuse for an off-grid electrical system.

Powering an off grid shepherds hut or glamping pod

01It has to look after itself

An off grid shepherds hut or glamping pod let to guests has to look after itself. For example, the system must cope with a guest who leaves a heater on, without anyone touching it. We set the MultiPlus-II and the battery protection so the battery is never run too low, whatever is plugged in.

02High power loads

We either design high power loads such as kettles, hair dryers and electric heaters in properly, or keep them off the system. So good shepherds hut electrics settle that at design stage, not after the first complaint.

03Monitoring

Above all, monitoring is the big win for owners. A Cerbo GX MK3 reports each off grid battery system to Victron VRM, so you see every unit’s state of charge from home, between bookings. Our battery monitoring guide and remote monitoring service cover the detail.

Engineer in a cap checking Victron GX settings on a laptop in front of an open cabinet with a Lynx Power In 1000 and a PV isolator
Checking a cabin system's Victron GX settings on the laptop, with the Lynx Power In and PV isolator in the cabinet behind. Photo: Unplugged

An off grid shepherds hut on a trailer, or a pod you can move, comes to our Witherslack workshop and goes home already tested. Site operators planning glamping pod power across several units should start with For Business.

BS 7671 inspection and testing: is an off grid cabin safe?

Yes, when we build and test both sides of the system properly. We treat them as two separate steps.

Step 1

The 230V side

A cabin is a fixed building. So we inspect and test its 230V installation to BS 7671, following IET Guidance Note 3: insulation resistance, polarity, earth fault loop impedance and RCD operation. We then issue an Electrical Installation Certificate. We design the earthing arrangement for a standalone supply, with the MultiPlus-II as the source.

Step 2

The battery and DC side

We inspect and check this as its own step, against BS 7671 Chapter 57 (stationary secondary batteries) and Section 712 (solar photovoltaic power supply systems). We also torque every DC connection to the maker’s figure and mark it with a torque pen. Our guide to BS 7671 Amendment 4 also explains what changed for cabins.

Two FuseBox consumer units labelled Danger 230 Volts, Warning Dual Supply and the periodic inspection notice, beside a generator inlet and a socket
The 230V side of a cabin system: two consumer units with dual-supply warning and periodic inspection labels, beside the generator inlet. Photo: Unplugged

Off grid cabins and off grid log cabin projects: how we help

We’re an Authorised Victron Energy Installer, and we supply and fit as one service. We design and build each off grid power system in our Witherslack workshop and test it before it leaves. On-site off grid solar installation is available on request, subject to review.

Unplugged off grid cabin on a UK hillside, powered by an off grid solar system on the roof
Photo: Unplugged

Customer story

Our work with Unplugged shows how off grid electrical power systems hold up across a run of guest cabins.

Building several off grid cabins, or running a site? If so, our off grid cabin electrics page for operators covers multi-unit projects and the questions that come with them.

Off grid solar system UK FAQs

How does off grid solar system work?

Solar panels feed an MPPT charge controller, which charges a lithium battery. A Victron MultiPlus-II inverter charger turns the stored energy into 230V for sockets and appliances, and can charge from a generator when the sun is weak. Finally, a Cerbo GX MK3 shows the whole system on one screen and online through VRM.

What is needed for off grid solar system?

Solar panels, an MPPT charge controller, a lithium battery, an inverter charger, DC fusing and isolation, and a metal consumer unit with double-pole RCBOs. Then add a Cerbo GX MK3 for monitoring. We size each part to your loads and site, and we inspect and test the 230V installation to BS 7671.

How much solar do I need to be off grid?

It depends on what you run, where the cabin sits and how much winter use you plan. Work out your daily use, size the battery to cover it for the days you need, then add enough solar to refill it in the darker months. So we size it from your loads and the site’s winter light.

Can I install my own off grid solar system?

You can plan it and build the low voltage side. However, a qualified electrician has to design, inspect, test and certify the 230V installation to BS 7671. Our Self-Build package gives you a custom kit and a wiring diagram drawn for your cabin, and we fit and test the rest.

Sources

  1. Victron Energy, MultiPlus-II 230V manual (installation: ground relay, generator input). victronenergy.com
  2. Victron Energy, Wiring Unlimited (system voltage and wiring principles). victronenergy.com
  3. Victron Energy, Lithium Battery Smart datasheet (LiFePO4 cycle life and efficiency). victronenergy.com
  4. Victron Energy, solar charge controllers. victronenergy.com
  5. Victron Energy, Cerbo GX and VRM. victronenergy.com
  6. IET, BS 7671:2018+A4:2026 Requirements for Electrical Installations (Chapter 57, Section 712) and Guidance Note 3. electrical.theiet.org
About the reviewer: Tom Alderdice

Tom holds the 18th Edition (BS 7671) and inspection and testing qualifications, plus NCC training in caravan and motorhome electrics.

Tiny Build Electrics is an Authorised Victron Energy Installer. See Tom’s full qualifications

Keep reading

More from the workshop

Where each fuse sits in a 12V lithium campervan system: a lithium leisure battery fuse at each battery post, then a Lynx Distributor with MEGA fuses for the MultiPlus, Orion XS and DC fuse box, and a dummy fuse in the fourth way for a SmartSolar MPPT 100/20 with its own inline 25 to 30A fuse on 6 mm² cableGuidesLithium leisure battery fuse sizing: how we protect every cablePublished · Updated Victron Energy Orion XS 12/12-50A DC-DC Battery Charger - ORI121217050GuidesLithium not charging while driving? Split charge relays, sizing your DC-DC and the Orion XS ‘no amps’ fixPublished · Updated Tiny Build Electrics electrician in a branded cap and jacket wiring a Victron solar charge controller and busbars inside a cabinet, with a Victron inverter on the shelf aboveGuidesDC-DC charger not charging: checks before you call it faultyPublished · Updated